Q97
In PERT analysis, the time estimates of activities and probability of their occurrence follow
A.
Normal distribution curve
B.
Poisson's distribution curve
C.
Beta distribution curve
AnswerD.
None of the above
Answer: Option C
Solution
Answer: Option C
No explanation is given for this question Let's Discuss on Board