In PERT, the span of time between the optimistic and pessimistic time estimate of an activity is
A.
3σ
B.
6σ
AnswerC.
12σ
D.
None of these
Answer: Option B
Solution
Answer: Option B
No explanation is given for this question Let's Discuss on Board