Vidyalelo
Management · Q217

Operations Research or Qualitative Approach

Graduate and Post Graduate · Management · question 217

Q217

In PERT, the span of time between the optimistic and pessimistic time estimate of an activity is

A.
B.
Answer
C.
12σ
D.
None of these

Answer: Option B

Solution

Answer: Option B
No explanation is given for this question Let's Discuss on Board