Vidyalelo
Management · Q218

Operations Research or Qualitative Approach

Graduate and Post Graduate · Management · question 218

Q218

The latest time that the event can be delayed without delaying the completion of the entire project in PERT chart is

A.
earliest allowable time
B.
latest allowable time
Answer
C.
earliest pass
D.
latest pass

Answer: Option B

Solution

Answer: Option B
No explanation is given for this question Let's Discuss on Board