In the given figure, the network of a project represents

In the given figure, the network of a project represents
Construction Planning and Management mcq question image
A.
Activity of an excavation of a footing
B.
Activity of an excavation which starts at event No. 1 and ends at even No. 2
C.
Activity of excavation which takes 8 units of time
Answer
D.
None of these

Answer: Option C

Solution

Answer: Option C
No explanation is given for this question Let's Discuss on Board