Q97
In the Three Gorges Dam project, what was the primary geological hazard?
A.
Lava flows
B.
Seismic activity and landslides
AnswerC.
Desertification
D.
Volcanic ash layers
Answer: Option B
Solution
Answer: Option B
Solution:
The project area is prone to seismic activity and landslides due to the steep river gorges and fault lines, requiring extensive slope stabilization and monitoring.