Q48
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
A.
Longest duration
B.
Highest cost slope
C.
Least cost slope
AnswerD.
Shortest duration
Answer: Option C
Solution
Answer: Option C
No explanation is given for this question Let's Discuss on Board