Vidyalelo
Civil Engineering · Q43

Construction Planning And Management

Engineering and GATE · Civil Engineering · question 43

Q43

In time-cost optimization of a project, crashing is done.

A.
On all the activities
B.
On all the activities lying on the critical path
C.
Only on activities lying on the original critical path and having flatter cost slopes
D.
On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board