Q115
In two days A, B and C together can finish 1/2 of a work and in another 2 days B and C together can finish 310 part of the work. Then A alone can complete the whole work in ?
In two days A, B and C together can finish of a work and in another 2 days B and C together can finish part of the work. Then A alone can complete the whole work in ?
A.
15 days
B.
10 days
AnswerC.
12 days
D.
14 days
Answer: Option B
Solution
Answer: Option B
Solution:
L.C.M of total work = 20
One day work of A + B + C = = 5 unit/day
One day work of B + C = = 3 unit/day
A = 5 - 3 = 2
A alone will complete the work