X, Y and Z complete a work in 6 days. X or Y alone can do the same work in 16 days. In how many days Z alone can finish the same work ?

A.
12
B.
16
C.
24
Answer
D.
36

Answer: Option C

Solution

Answer: Option C
Solution:
(X + Y)'s 1 day's work

∴ Z's 1 day's work
(X + Y + Z)'s 1 day's work - (X + Y)'s 1 day's work

∴ Z alone can finish the work in 24 days.