Latest start of an activity is always

A.
greater than or equal to latest event time of preceding node
Answer
B.
less than or equal to latest event time of preceding node
C.
equal to latest event time of preceding node
D.
less than latest event time of preceding node

Answer: Option A

Solution

Answer: Option A