Q182
PERT analysis is based on
A.
Optimistic time
B.
Pessimistic time
C.
Most likely time
D.
All of the above
AnswerAnswer: Option D
Solution
Answer: Option D
Solution:
PERT Analysis. Program Evaluation and Review Technique (PERT) is a method used to examine the tasked that are in a schedule and determine a variation of the Critical Path Method (CPM).It analyzes the time required to complete each task and its associated dependencies to determine the minimum time to complete a project