Vidyalelo
Mechanical Engineering · Q182

Industrial Engineering And Production Management

Engineering and GATE · Mechanical Engineering · question 182

Q182

PERT analysis is based on

A.
Optimistic time
B.
Pessimistic time
C.
Most likely time
D.
All of the above
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
PERT Analysis. Program Evaluation and Review Technique (PERT) is a method used to examine the tasked that are in a schedule and determine a variation of the Critical Path Method (CPM).
It analyzes the time required to complete each task and its associated dependencies to determine the minimum time to complete a project