Q183
Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it
A.
Consumes time, but no resources
B.
Consumes resources but no time
C.
Consumes neither time nor resources
AnswerD.
Is a dangling event
Answer: Option C
Solution
Answer: Option C
Solution:
Dummy activity on a PERT/CPM chart means, it Consumes neither time nor resources