Q282
PERT analysis is based upon
A.
Optimistic time
B.
Pessimistic time
C.
Most likely time
D.
All of these
AnswerAnswer: Option D
Solution
Answer: Option D
Solution:
PERT analysis is based uponOptimistic time
Pessimistic time
Most likely time