Q283
Pessimistic time is
A.
The maximum time which an activity might require
AnswerB.
The average time required for a job
C.
The most probable time considering all conditions
D.
The minimum time in which an activity can possibly be accomplished
Answer: Option A
Solution
Answer: Option A
Solution:
Pessimistic time is a concept used in the program evaluation and review technique (PERT). It represents the longest estimated time period within which a task is likely to be completed, and is used in project planning.