Pick up the correct statement from the following:

A.
The difference of latest occurrence time and earliest expected time, is called slack
B.
The activities connecting the events having zero slack, lie on the critical path
C.
The critical path consumes the maximum time
D.
All the above
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board