Pick up the correct statement from the following:

A.
In order to check up the average depth of excavation, 'Dead man’s' are left at the mid-widths of borrow pits
B.
The earthwork calculation in excavation is made from the difference in levels obtained with a level
C.
The earth work in excavation to form the road embankment includes the formation of correct profile and depositing the soil in layers
D.
All the above
Answer

Answer: Option D

Solution

Answer: Option D