Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

A.
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
B.
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
C.
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
D.
All the above
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board