Pick up the incorrect statement from the following:

A.
The activity is the time consuming part of a project
B.
The beginning and end of a job, are called events
C.
The activity which consumes maximum time, is called a node
Answer
D.
Logically and sequentially connected activities and events form a network

Answer: Option C