Q105
Pick up the incorrect statement from the following:
A.
The activity is the time consuming part of a project
B.
The beginning and end of a job, are called events
C.
The activity which consumes maximum time, is called a node
AnswerD.
Logically and sequentially connected activities and events form a network
Answer: Option C
Solution
Answer: Option C
No explanation is given for this question Let's Discuss on Board