Q100
Pick up the PERT event from the following:
A.
Digging of foundation started
B.
Digging of foundation completed
C.
Laying of concrete started
D.
All the above
AnswerAnswer: Option D
Solution
Answer: Option D
No explanation is given for this question Let's Discuss on Board