Q353

Risk of premature collapse and over-ridding of pillars are maximum with

A.
shortwall method
B.
longwall
C.
bord and pillar
Answer
D.
sub-level caving

Answer: Option C

Solution

Answer: Option C
No explanation is given for this question Let's Discuss on Board