Vidyalelo
Civil Engineering · Q111

Construction Planning And Management

Engineering and GATE · Civil Engineering · question 111

Q111

Select the correct statement.

A.
Activity arrows in a CPM network are drawn to scale
B.
The tail of an arrow represents the finish of an activity
C.
Arrow bead represents the start of an activity
D.
None of the above
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board