Q111
Select the correct statement.
A.
Activity arrows in a CPM network are drawn to scale
B.
The tail of an arrow represents the finish of an activity
C.
Arrow bead represents the start of an activity
D.
None of the above
AnswerAnswer: Option D
Solution
Answer: Option D
No explanation is given for this question Let's Discuss on Board