Vidyalelo
Civil Engineering · Q119

Construction Planning And Management

Engineering and GATE · Civil Engineering · question 119

Q119

The constraints in case of resource smoothening operation would be

A.
Resources
B.
Project duration time
Answer
C.
Both resources and project duration time
D.
None of the above

Answer: Option B

Solution

Answer: Option B
No explanation is given for this question Let's Discuss on Board