Vidyalelo
Civil Engineering · Q25

Estimating And Costing

Engineering and GATE · Civil Engineering · question 25

Q25

The detention period in a septic tank is assumed

A.
20 minutes
B.
25 minutes
C.
30 minutes
Answer
D.
40 minutes

Answer: Option C

Solution

Answer: Option C
No explanation is given for this question Let's Discuss on Board