Q21

The difference between the time available to do the job and the time required to do the job, is known as

A.
Event
B.
Float
Answer
C.
Duration
D.
Constraint

Answer: Option B

Solution

Answer: Option B
Solution:
The difference between the time available to do the job and the time required to do the job is known as Float