Vidyalelo
Geological Engineering · Q194

Case Studies and Applied Geological Engineering Projects

Engineering and GATE · Geological Engineering · question 194

Q194

The East-West Metro Tunnel under the Hooghly river was executed using:

A.
Cut-and-cover method
B.
Tunnel boring machines (TBM)
Answer
C.
Drilled shaft tunneling
D.
Immersed tube method

Answer: Option B

Solution

Answer: Option B
Solution:
The East-West Metro in Kolkata used a tunnel boring machine (TBM) to excavate the river crossing beneath the Hooghly. This method minimized surface disturbance and managed soft ground.