Q46
The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is
A.
1.00 m3
B.
1.25 m3
AnswerC.
1.50 m3
D.
1.75 m3
Answer: Option B
Solution
Answer: Option B
No explanation is given for this question Let's Discuss on Board