The feasibility study of an opencast mine revealed the following: Recoverable value per tonne of ore = Rs. 900 Production cost per tonne of ore = Rs. 550 Stripping cost per tonne of waste = Rs. 45 The break even stripping ratio will be

A.
7.77
Answer
B.
32.20
C.
1.78
D.
12.22

Answer: Option A

Solution

Answer: Option A