Q182
The latest time at which activities terminating at an event can be completed and still permit the entire project to be finished on schedule is
A.
earliest allowable time
B.
latest allowable time
AnswerC.
earliest pass
D.
latest pass
Answer: Option B
Solution
Answer: Option B
No explanation is given for this question Let's Discuss on Board