The stoping method, where a large part of blasted ore is allowed to accumulate in the stope to serve the purpose of providing working platform for stoping as well as to support the wall-rock, is known as
A.
shrinkage stoping
AnswerB.
cut and fill stoping
C.
square-set stoping
D.
sublevel stoping
Answer: Option A