The time study data of an equipment deployed in a mine during a calendar month is given below. Total working hours = 400 Total maintenance hours = 100 Total hours of actual work = 240 The percentage of utilization of the equipment is

A.
85
Answer
B.
80
C.
65
D.
60

Answer: Option A

Solution

Answer: Option A
No explanation is given for this question Let's Discuss on Board