Q279

The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days ?

A.
4 days
B.
2 days
C.
1 day
Answer
D.
10 days

Answer: Option C

Solution

Answer: Option C
Solution: