Q70
Total float for any activity is defined as the difference between
A.
Its latest finish time and earliest start time for its successor activity
B.
Its latest start time and earliest start time
AnswerC.
Its latest start time and earliest finish time
D.
Its earliest finish time and earliest start time for its successor activity
Answer: Option B
Solution
Answer: Option B
No explanation is given for this question Let's Discuss on Board