Civil Engineering · Q121

Construction Planning And Management

Engineering and GATE · Civil Engineering · question 121

Q121

While scheduling a project by C.P.M.

A.
A project is divided into various activities
B.
Required time for each activity is established
C.
Net work is drawn by connecting the activities and the events
D.
All the above
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board