X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 16 days, Y can alone finish that work in:

A.
27 days
B.
36 days
Answer
C.
42 days
D.
18 days

Answer: Option B

Solution

Answer: Option B
Solution:
Time and Work mcq question image
According to the question,
X → 24 days
⇒ Work done by X in 4 days alone = 4 × 1 = 4 units
⇒ Remaining work = 24 - 4 = 20 units
⇒ 20 units done by both together in (16 - 4 days) = 12 days
⇒ Then efficiencies of (X + Y)
⇒ Efficiency of Y =
⇒ Time taken by Y alone to complete the total work

Alternate solution:

Efficiency of Y = 5 - 3 = 2 units/day
Total work = 24 × 3 = 72 units
Total time taken by Y = = 36 days