A software component
A. Implements some functionality
B. Has explicit dependencies through provides and required interfaces
C. Communicates through its interfaces only
D. All of the mentioned
Select an option to see the answer and solution.
Which of the following is not a real-time architectural pattern
A. Observe and React
B. Environmental Control
C. Embedded System
D. Process Pipeline
Select an option to see the answer and solution.
Which model is used to compute the effort required to integrate reusable components or program code that is automatically generated by design or program translation tools?
A. An application-composition model
B. A post-architecture model
C. A reuse model
D. An early design model
Select an option to see the answer and solution.
Which of the following is a software process ?
A. Analysis and design
B. Configuration and management
C. Business modeling
D. All of the mentioned
Select an option to see the answer and solution.
Which of the following is not an appraisal cost in SQA?
A. inter-process inspection
B. maintenance
C. quality planning
D. testing
Select an option to see the answer and solution.
Which of the following is one of the steps in the integration testing of OO software?
A. cluster testing
B. thread-based testing
C. use-based testing
D. none of the mentioned
Select an option to see the answer and solution.
Which of the following is a design pattern?
A. Behavioral
B. Structural
C. Abstract Factory
D. All of the mentioned
Select an option to see the answer and solution.
Which of the following is an indirect measure of product?
A. Quality
B. Complexity
C. Reliability
D. All of the Mentioned
Select an option to see the answer and solution.
Which of the following errors should not be tested when error handling is evaluated?
A. Error description is unintelligible
B. Error noted does not correspond to error encountered
C. Error condition causes system intervention prior to error handling
D. Error description provide enough information to assist in the location of the cause of the error
Select an option to see the answer and solution.
Identify a fourth generation language(4GL) from the given below.
A. FORTRAN
B. COBOL
C. Unix shell
D. C++
Select an option to see the answer and solution.
A project usually has a timeline chart which was developed by
A. Henry Gantt
B. Barry Boehm
C. Ivar Jacabson
D. None of the mentioned
Select an option to see the answer and solution.
How is generalization implemented in Object Oriented programming languages?
A. Inheritance
B. Polymorphism
C. Encapsulation
D. Abstract Classes
Select an option to see the answer and solution.
Which of these does not affect different types of software as a whole?
A. Heterogeneity
B. Flexibility
C. Business and social change
D. Security
Select an option to see the answer and solution.
What is normally considered as an adjunct to the coding step
A. Integration testing
B. Unit testing
C. Completion of Testing
D. Regression Testing
Select an option to see the answer and solution.
How is software reliability defined?
A. time
B. efficiency
C. quality
D. speed
Select an option to see the answer and solution.
Which of the following is not a main phase in Configuration Management (CM) Process?
A. CM Planning
B. Executing the CM process
C. CM audits
D. None of the mentioned
Select an option to see the answer and solution.
A . . . . . . . . is developed using historical cost information that relates some software metric to the project cost.
A. Algorithmic cost modelling
B. Expert judgement
C. Estimation by analogy
D. Parkinson's Law
Select an option to see the answer and solution.
What is the recommended distribution of effort for a project?
A. 40-20-40
B. 50-20-30
C. 30-40-30
D. 50-30-20
Select an option to see the answer and solution.
Project management involves the planning, monitoring, and control of the people, process, and events that occur as software evolves from a preliminary concept to an operational implementation.
Select an option to see the answer and solution.
Which of the following term is best defined by the statement:"the degree of uncertainty that the product will meet its requirements and be fit for its intended use."?
A. Performance risk
B. Cost risk
C. Support risk
D. Schedule risk
Select an option to see the answer and solution.