Q401
Open questionIn shovel loading of broken iron ore, if loading cycle time of the shovel of 5 m3 bucket capacity, is 60 seconds, bucket fill ratio is 0.8, rock looseness factor is 1.5 and shovel working time utilization factor is 0.6, then the hourly output of the shovel in m3/hr will be
Select an option to see the answer and solution.