"Calculate re-order level from the following:
Safety stock: 1000 units
Consumption per week: 500 units
It takes 12 weeks to reach material from the date of ordering"
"From the following information, calculate the extra cost of material by following EOQ:
Annual consumption = 45000 units
Ordering cost per order = Rs 10
Carrying cost per unit per annum = Rs 10
Purchase price per unit = Rs 50
Re-order quantity at present = 45000 units
There is discount of 10% per unit in case of purchase of 45000 units in bulk"
"Calculate workers left and discharged from the following:
Labour turnover rates are 20%, 10% and 6% respectively under Flux method, Replacement method and Separation method No of workers replaced during the quarter is 80"
"Calculate workers recruited and joined from the following:
Labour turnover rates are 20%, 10% and 6% respectively under Flux method, Replacement method andSeparation method No of workers replaced during the quarter is 80"
Calculate the labour turnover rate according to replacement method from the following:
No of workers on the payroll:
- At the beginning of the month: 500
- At the end of the month: 600
During the month, 5 workers left, 20 workers were discharged and 75 workers were recruited Ofthese, 10 workers were recruited in the vacancies of those leaving and while the rest were engaged for an expansion scheme
Calculate the labour turnover rate according to Separation method from the following:
No of workers on the payroll:
- At the beginning of the month: 500
- At the end of the month: 600
During the month, 5 workers left, 20 workers were discharged and 75 workers were recruited Of these, 10 workers were recruited in the vacancies of those leaving and while the rest were engaged for an expansion scheme
A worker is allowed 60 hours to complete the job on a guaranteed wage of Rs 10 per hour Under the Rowan Plan, he gets an hourly wage of Rs 12 per hour For the same saving in time, how much he will get under the Halsey Plan?
AT Co makes a single product and is preparing its material usage budget for next year Each unit of product requires 2kg of material, and 5,000 units of product are to be produced next year Opening inventory of material is budgeted to be 800 kg and AT co budgets to increase material inventory at the end of next year by 20%.
The material usage budget for next year is
"During September, 300 labour hours were worked for a total cost of Rs. 4800 The variable overhead expenditure variance was Rs. 600 (A) Overheads are assumed to be related to direct labour hours of active working.
What was the standard cost per labour hour?"