Mining Engineering · Q132

Introduction to Mining Engineering

Engineering and GATE · Mining Engineering · question 132

Q132

A 15 m3 dragline is deployed in an O.B. bench of an O.C. mine. It works for 40 days at the rate of 6 hrs per shift and 3 shifts a day. The cycle time, bucket fill factor, and operating efficiency of the dragline are respectively 50 s, 0.8, and 75%. The total volume of O.B. in m3 handled by the dragline is

A.
356918
B.
365918
C.
532158
D.
466560
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board