For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is
A.
8 days
B.
9 days
AnswerC.
10 days
D.
15 days
Answer: Option B
Solution
Answer: Option B