For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is

A.
8 days
B.
9 days
Answer
C.
10 days
D.
15 days

Answer: Option B

Solution

Answer: Option B
No explanation is given for this question Let's Discuss on Board