For the network shown in the given figure, the expected time for the activity

For the network shown in the given figure, the expected time for the activity
Construction Planning and Management mcq question image
A.
1-2 is 4
B.
2-3 is 7
C.
3-4 is 8
D.
All the above
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board