Q62
For completion of a project, the critical path of the network represents
A.
Minimum time
AnswerB.
Maximum time
C.
Maximum cost
D.
Minimum cost
Answer: Option A
Solution
Answer: Option A
No explanation is given for this question Let's Discuss on Board