Civil Engineering · Q61

Construction Planning And Management

Engineering and GATE · Civil Engineering · question 61

Q61

Which of the following is a weakness of bar chart?

A.
Interdependencies of activities
B.
Project progress
C.
Uncertainties
D.
All of the above
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board