Civil Engineering · Q60

Construction Planning And Management

Engineering and GATE · Civil Engineering · question 60

Q60

If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

A.
expected time of activity A is greater than the expected time of activity B
B.
expected time of activity B is greater than the expected time of activity A
C.
expected time of both activities A and B are same
Answer
D.
none of the above

Answer: Option C

Solution

Answer: Option C
No explanation is given for this question Let's Discuss on Board