Q60
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then
A.
expected time of activity A is greater than the expected time of activity B
B.
expected time of activity B is greater than the expected time of activity A
C.
expected time of both activities A and B are same
AnswerD.
none of the above
Answer: Option C
Solution
Answer: Option C
No explanation is given for this question Let's Discuss on Board