Vidyalelo
Civil Engineering · Q124

Construction Planning And Management

Engineering and GATE · Civil Engineering · question 124

Q124

If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

A.
Started 5 days later
B.
Completed 5 days later
C.
Performed at slower rate in 15 days
D.
All the above
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board