Q124
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
A.
Started 5 days later
B.
Completed 5 days later
C.
Performed at slower rate in 15 days
D.
All the above
AnswerAnswer: Option D
Solution
Answer: Option D
No explanation is given for this question Let's Discuss on Board