Q125
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is


A.
20
B.
25
AnswerC.
35
D.
15
Answer: Option B
Solution
Answer: Option B
No explanation is given for this question Let's Discuss on Board