Engineering and GATE · Civil Engineering · question 125

Q125

Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
Construction Planning and Management mcq question image
A.
20
B.
25
Answer
C.
35
D.
15

Answer: Option B

Solution

Answer: Option B
No explanation is given for this question Let's Discuss on Board