Vidyalelo
Civil Engineering · Q126

Construction Planning And Management

Engineering and GATE · Civil Engineering · question 126

Q126

The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is

The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
Construction Planning and Management mcq question image
A.
19
Answer
B.
14
C.
24
D.
None of these

Answer: Option A

Solution

Answer: Option A
No explanation is given for this question Let's Discuss on Board