A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be

Select an option to see the answer and solution.

A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will

Select an option to see the answer and solution.

The time with which direct cost does not reduce with the increase in time is known as

Select an option to see the answer and solution.

If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is

Select an option to see the answer and solution.

For a given size of bucket, the ideal output of a dragline will be least in

Select an option to see the answer and solution.

Frederick W. Taylor introduced a system of working known as

Select an option to see the answer and solution.

For the execution of a project, a contractor is

Select an option to see the answer and solution.

An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?

Select an option to see the answer and solution.

Works costing less than Rs. 20,000 are treated as

Select an option to see the answer and solution.

If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is

Select an option to see the answer and solution.

A dummy activity

Select an option to see the answer and solution.

A Milestone chart

Select an option to see the answer and solution.

Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of project
PERT is preferred for planning because of

Select an option to see the answer and solution.

Consider the following statements:
In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated.

Select an option to see the answer and solution.

Batching refers to

Select an option to see the answer and solution.

Military organization is known as

Select an option to see the answer and solution.

Critical path lies along the activities having total float

Select an option to see the answer and solution.

An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is

Select an option to see the answer and solution.

Slack time refers to

Select an option to see the answer and solution.

The most suitable type of equipment for compaction of cohesive soils is

Select an option to see the answer and solution.