In a cut-and-fill stope, the main purpose of back filling is to

Select an option to see the answer and solution.

Maximum Lump size that can be conveyed by belt conveyer is

Select an option to see the answer and solution.

How much time a dragline may take to complete a cycle for a single pass?

Select an option to see the answer and solution.

A narrow vertical or inclined excavation made in the ore block along the width and the height of a stope to continue stoping is termed as

Select an option to see the answer and solution.

Two coal seams are called contiguous if they are A m (maximum) apart from each other. A is given by

Select an option to see the answer and solution.

The sale value of chromite ore from an open pit mine is Rs. 6500 per tonne. Cost of mining, excluding stripping cost, is Rs. 2450 per tonne. If the cost of stripping is Rs. 1150 per m3, the breakeven stripping ratio in m3/tonne is

Select an option to see the answer and solution.

From a hard rock open pit mine, the following data available
Burden : 3 m
Spacing : 4 m
Bench height : 12 m
Sub-drilling : 1 m
Collar stemming : 4 m
Diameter of hole : 150 mm
Density of rock : 2500 kg/m3
Density of explosive : 800 kg/m3
The powder factor in kg/t is

Select an option to see the answer and solution.

As per the Indian Electricity Rules 1956. the maximum permissible length of a flexible cable used with an electric rope shovel in m is

Select an option to see the answer and solution.

The slope angle for hard and compact ground should not be more than

Select an option to see the answer and solution.

The opening cut in open cast mining is known as

Select an option to see the answer and solution.

Advance supporting of 30 m at both the gate roads is required due to

Select an option to see the answer and solution.

A 15 m3 dragline is deployed in an O.B. bench of an O.C. mine. It works for 40 days at the rate of 6 hrs per shift and 3 shifts a day. The cycle time, bucket fill factor, and operating efficiency of the dragline are respectively 50 s, 0.8, and 75%. The total volume of O.B. in m3 handled by the dragline is

Select an option to see the answer and solution.

Mine life time should be calculated based on

Select an option to see the answer and solution.

No mode or type of Capping shall be used which fails to withstand a load of atleast "N" times the maximum static load. N is given by

Select an option to see the answer and solution.

Over 80% of underground coal production in India comes from

Select an option to see the answer and solution.

The following data are provided for a surface mine to be excavated by a shovel:
Production target : 10000 te/shift
Available hours per shift : 6 hrs
Shovel loading cycles per hour : 106
Bank density of the material mined : 2400 kg/m3
Swing factor at 120° swing : 0.91
Bucket fill factor : 0.64
Utilization of available time : 83%
No of working days in a year : 300
No of shifts per day : 3
The annual production target in Mte is

Select an option to see the answer and solution.

Select the correct order with respect to the core sizes

Select an option to see the answer and solution.

A non-electric detonating relay does not contain

Select an option to see the answer and solution.

Which of the following sampling technique is followed during sampling from wagons or dumps in the form of scoop taken at regular intervals?

Select an option to see the answer and solution.

Value of Bulking Factor is

Select an option to see the answer and solution.