The most common system of stope extraction is to maintain as . . . . . . . .
A. Diagonal line of extraction
B. Horizontal line of extraction
C. Vertical line of extraction
D. None
Select an option to see the answer and solution.
In shrinkage stoping the inclination of stope wall should be . . . . . . . .
Select an option to see the answer and solution.
Extraction of small sized, irregularly unsystamatic underground working called
A. Sub level stoping
B. Top slicing
C. Block caving
D. Gophering
Select an option to see the answer and solution.
For a successful VCR stoping, which of the following is appropriate.
A. Large dia blast holes
B. Spherical explosive charges
C. Vertical downward blast hole
D. All
Select an option to see the answer and solution.
Capacity of slusher is . . . . . . . . tph.
A. 30 - 40
B. 40 - 60
C. 10 - 20
D. 70 - 100
Select an option to see the answer and solution.
The raise boring consists essentially of drilling a pilot hole of diameter . . . . . . . .
A. 0 - 50mm
B. 60 - 120mm
C. 150 - 200mm
D. 230 - 300mm
Select an option to see the answer and solution.
The main advantage of drop raising is that number of workers in the lower level are . . . . . . . . except the operator of LHD.
Select an option to see the answer and solution.
A system of vertical or nearly vertical openings for transfering ore from a stope to a single delivery point.
A. Draw point
B. Ore pass
C. Grizzley
D. Finger rise
Select an option to see the answer and solution.
In this method needs heavy supports comparative than other methods and also supporting costly.
A. Breast
B. Shrinkage
C. Square set
D. Sub level
Select an option to see the answer and solution.
The method used for mining narrow veins or pay streaks, where ore occurs as a distinct band, can be separated easily from wall rocks, mining known as . . . . . . . .
A. Room and pillar
B. Wide stall
C. Integral caving
D. Resuing
Select an option to see the answer and solution.
The first or lowest slice often referred as . . . . . . . .
A. Back stope
B. Breast stope
C. Lead stope
D. None
Select an option to see the answer and solution.
Costliest stoping method is . . . . . . . .
A. Cut and fill
B. Square set
C. Sub level
D. Block caving
Select an option to see the answer and solution.
The most precise and fast collection of samples, the method is . . . . . . . . in u/g.
A. Channel
B. Chip
C. Drill
D. Wagon
Select an option to see the answer and solution.
In this mining method, in which masses, panels or block of ore are under cut to induce caving, permitting the broken ore to be drawn off below.
A. Sub level
B. Block caving
C. Integral caving
D. Top slicing
Select an option to see the answer and solution.
The foot wall shaft cross cuts are drawn to intersect the ore body and raises are made to connect the cross cuts; in under ground. The top of the raises are widened, the method of extraction is . . . . . . . .
A. Open under hand stopin
B. Open over hand stoping
C. u/g glory hole
D. Breast stoping
Select an option to see the answer and solution.
The deposit of iron ore in India is about . . . . . . . . % of the world.
Select an option to see the answer and solution.
Excess pore pressure in backfill material is a cut and fill stope leads to . . . . . . . .
A. Loss of shear resistance to fill
B. Reductionin strength of the wall rock
C. Enhance bearing strength to fill
D. Prevents of progressive failure of crown pillar
Select an option to see the answer and solution.
Ore grade from which revenue from the recoverable reserves exactly equals to the cost of mining, treatment and marketing is called . . . . . . . .
A. Cut off grade
B. Average grade
C. Break even grade
D. None
Select an option to see the answer and solution.
Raise driving by use of jora hoist to drive mechanised raising upto . . . . . . . . m long raises.
Select an option to see the answer and solution.
The ring drilling and blasting employed in this stoping.
A. Breast
B. VCR
C. Conventional sublevel
D. Cut and fill
Select an option to see the answer and solution.