For transferring the tunnel alignment through shafts, we adopt the following steps:
1.Hanging two or more plumb lines in the shaft
2.Determining the bearing of the plumb lines i.e. plumb plane
3.Suspending a 35 kg weight by each plumb line
4.Immersing the weights of both the plumb lines in the buckets containing water
The correct sequence of steps is:

Select an option to see the answer and solution.

Which one of the following is considered to be an advantage of the heading and benching method of tunnel construction?

Select an option to see the answer and solution.

Which one of the following methods is generally adopted for tunnelling in firm ground

Select an option to see the answer and solution.

Which of the following is not a component of the shield?

Select an option to see the answer and solution.

Which one of the following statements is not correct for heading and benching method of tunnelling?

Select an option to see the answer and solution.

Which one of the following statements is not correct with regard to heading and henching method of tunnelling?

Select an option to see the answer and solution.

What is the correct sequence of the following events in rock tunnelling?
1. Marking tunnel profile
2. Loading explosives and blasting
3. Checking misfire
4. Mucking
5. Removing foul gas
6. Setting up and drilling
7. Guniting
Select the correct answer

Select an option to see the answer and solution.

An overhead track on a large truss frame is required in case of car changer by

Select an option to see the answer and solution.

Pick up the explosive used for tunnelling in soft rocks from the following:

Select an option to see the answer and solution.

Pick up the mechanical ventilation method used for tunnels from the following:

Select an option to see the answer and solution.

Pick up the correct statement regarding drilling a tunnel from the following:

Select an option to see the answer and solution.

Pick up the correct statement from the following:

Select an option to see the answer and solution.

If ‘N’ is the number of shafts used, then the total number of faces available for attacking the excavation and construction in tunnels are

Select an option to see the answer and solution.

For highways, tunnelling is preferred to if the open cut exceeds:

Select an option to see the answer and solution.

Forepoling method is generally adopted for tunnelling in:

Select an option to see the answer and solution.

A tunnel is found more advantageous as compared to the alternate routes because it:

Select an option to see the answer and solution.

The needle beam method of tunnelling
(i) Is suitable for soils in which roof can stand for few minutes without support
(ii) Is suitable for brick lining
(iii) Is suitable for concrete lining
(iv) Requires large number of trench jacks

Select an option to see the answer and solution.

Concrete lining is provided concurrently with the driving operation in case of

Select an option to see the answer and solution.

In “full face” method of constructing tunnels, the first operation relates to

Select an option to see the answer and solution.

The following operations are generally employed for tunnelling in hard rock.
1.Removing ground water,
2.Loading holes and firing the explosive
3.Setting up and drilling
4.Grouting and lining
5.Removing muck
6.Ventilation and removing explosion dust
The correct sequence is:

Select an option to see the answer and solution.